China Petrochemical News Network News Yanshan Petrochemical's new melt blown cloth production line project is progressing smoothly. During the installation of the equipment, a three-dimensional crossover work network was formed on the project site. All the construction staff actively benchmarked the construction speed of Huoshenshan and Leishenshan Hospitals, and every second counts and pays close attention to the progress. After 5 days and 5 nights of hard work, as of 3:30 am on March 5th, the net forming machine, electret machine, slitting machine, winder and other large key equipment that arrived at the end have been installed in place. The project Started to enter the trial production stage.
On February 29, the main plant equipment foundation of the Yanshan Petrochemical Meltblown Cloth Production Line Project was completed, and the project construction began to transfer to the equipment installation stage, and the battle for large-scale key equipment installation began.
The first installation is the steel structure, process piping and high and low voltage switch cabinets. At around midnight on the 29th, the hoisting operation of the 7 columns and steel beams of the main equipment frame and the installation of the operating platform began. After nearly 6 hours of hoisting construction, the columns and steel beams were hoisted and installed in place, and the steel structure assembly of the operating platform was basically completed by noon on March 1. Starting at noon, the construction crew worked together again, hoisting the 4 main fans into place.
At 0:30 midnight on March 2nd, Yanshan Petrochemical's new meltblown non-woven fabric production line project site roared and bright as daylight. The 450-ton crawler crane uses a long boom to hoist a melt-blown steel lifting platform w